On a lot of jobs, the change order log grows all year and nobody wants to deal with it. "We'll settle up at the end." Then the end comes, the GC has closeout pressure from the owner, you need the money, and the whole pile gets negotiated in one meeting. It rarely goes well for the sub.
Why closeout is the worst time to negotiate
- Your leverage is gone. Mid-job, the GC needs your crew. At closeout, the work is done.
- The evidence is stale. The foreman who knows why the conduit was rerouted has moved to another job. Photos are scattered across phones.
- Everything gets bundled. Strong claims and weak ones get averaged together into a single number, and the strong ones subsidize the discount on the weak.
- Cash pressure. If you're carrying the cost of the changes, a quick settlement starts to look better than a fair one.
Price time, not just money
The hardest costs to recover later are the ones that don't show up on a materials invoice: working out of sequence, stacking trades, overtime to hold a schedule someone else blew, and lost productivity.
- Ask for time in every change order, even when you think you won't need it. A change that adds no days on paper becomes hard to connect to a delay later.
- Note the impact the day it happens. "Crew of six held for two hours waiting on framing in area C" in a daily report is worth far more than a reconstruction months later.
Watch what you sign along the way
Many change order forms include language that the change order is "full and final" compensation for that change, including all delay and impact costs. If you sign that on a small change while bigger impacts are still unfolding, you may have settled them too.
- Reserve your rights. Add a short line before you sign: "Time and impact costs are reserved and will be submitted separately."
- Read pay applications the same way. Some include a statement that all claims to date are resolved. List open change orders as exceptions.
- Be careful with "payment in full" checks. Cashing a check marked as full payment of a disputed amount can, in some situations, settle the dispute. Talk to counsel before you deposit one.
Keep the log moving
- Submit pricing within days, not weeks, while the facts are fresh.
- Review the open log with the GC's project manager every month, item by item.
- Escalate anything older than 60 days to someone with authority on both sides.
- Bill approved changes in the next pay application.
- Decide early which disputes are worth pursuing. A claim that costs more to prove than it will recover is better traded for something else now.
Ask for it in the subcontract
- A deadline for the GC to respond to change order requests
- Payment for undisputed change work in the next pay cycle
- Time extensions considered with every change, not separately
- A clear process for directed work while the price is disputed
Change orders are easiest to collect when they're small, recent and documented. Treat the log as receivables, not a list of arguments for later.